The department of health, construction review, must receive and approve preinstallation submissions prior to installation. Preinstallation submissions may include any or all of the following:
(1) Stamped shop drawings, hydraulic calculations, and equipment information sheets for fire sprinkler system(s);
(2) Shop drawings, battery calculations, and equipment information sheets for fire detection and alarm systems;
(3) Shop drawings and equipment information sheets for a kitchen hood and duct automatic fire extinguishing system;
(4) Drawings and equipment information sheets for special egress control devices; and
(5) Drawings and/or a finish schedule denoting areas to be carpeted with:
(a) A coding system identifying type of carpet in each area;
(b) A copy the manufacturer's specifications for each type of carpet; and
(c) A copy of a testing laboratory report of the radiant panel and smoke density tests for each type of carpet.