(1) The required RFP issued pursuant to WAC 480-107-009(2) must comply with all sections of this chapter except WAC 480-107-021 requiring an informational filing.
(2) A targeted RFP filed with a required RFP under WAC 480-107-009(2) must comply with all sections of this chapter except WAC 480-107-021 requiring an informational filing.
(3) A voluntary RFP issued pursuant to WAC 480-107-009(3) must comply with all sections of this chapter except WAC 480-107-017 requiring commission approval.
(4) For all other actions by the utility to acquire resources not included in WAC 480-107-009, the utility must comply with WAC 480-107-115.