HTML has links - PDF has Authentication
463-72-010  <<  463-72-020 >>   463-72-030

PDFWAC 463-72-020

Plan elements.

Site restoration or preservation plans shall be prepared in sufficient detail to identify, evaluate, and resolve all major environmental and public health and safety issues, to include provisions for funding or bonding and monitoring. Specific plans shall:
(1) Describe the process and/or assumptions used to evaluate the options considered and the measures selected to restore or preserve the site to protect the environment and all segments of the public against risks and dangers resulting from the site operations and activities.
(2) Address provisions for funding or bonding to meet restoration or preservation costs. Financial assurance shall be provided to ensure that funding is available and sufficient for site restoration or preservation. Such financial assurances shall include evidence of pollution liability insurance coverage in an amount justified for the project, and a site closure bond, sinking fund, or other financial instrument or security in an amount justified in the initial site restoration plan.
(3) Address the scope of monitoring to be conducted during site restoration or preservation and possible continued monitoring to ensure site restoration is achieved.
[Statutory Authority: RCW 80.50.040 (1) and (12). WSR 04-21-013, ยง 463-72-020, filed 10/11/04, effective 11/11/04.]
Site Contents
Selected content listed in alphabetical order under each group