Search
296-150F-0720  <<  296-150F-3000 >>   End of Chapter

WAC 296-150F-3000

Agency filings affecting this section

Factory-built housing and commercial structure fees.

  


GENERAL INFORMATION
Manufacture:   Manufacturer #
1. Building use:   2. Building occupancy:
3. Type of construction:   4. Square footage of building:
5. Valuation of the building shall be based on the following:
Square footage of the building multiplied by the amount in the

BVD valuation table . . . . . . . . . . . .
$ . . . . .
6. Total valuation: . . . . . . . . . . . . $ . . . . .
PERMIT FEE
7. Calculate from building permit fee table using the total valuation . . . . . . . . . . . . $ . . . . .
STRUCTURAL PLAN REVIEW FEE*
8. One year design review: (Valid for one year) multiply the total on line 7 by 0.35 . . . . . . . . . . . . $ . . . . .
9. Master plan review: (Valid for the code cycle) multiply the total on line 7 by 0.50 . . . . . . . . . . . . $ . . . . .
* Minimum plan review fee is 2 1/2 hours x $85.50 per hour
FIRE AND LIFE-SAFETY PLAN REVIEW FEE (if required)
10. Fire and life-safety plan review:      
a. One year design -- Multiply the total on line 7 by 0.15 . . . . . . . . . . . . $ . . . . .
b. Master plan design -- Multiply the total on line 7 by 0.25 . . . . . . . . . . . . $ . . . . .
Required for all structures that are more than 4,000 square feet and for all A, I, and H occupancy
PLUMBING PLAN-REVIEW FEE
11. Plumbing $18.00 + $6.00 per fixture . . . . . . . . . . . . $ . . . . .
12. Medical gas $18.00 + $6.00 per gas outlet . . . . . . . . . . . . $ . . . . .
DESIGN RENEWAL OR ADDENDUM
13. 10% of building permit + $85.50 . . . . . . . . . . . . $ . . . . .
RESUBMITTAL
14. 10% of building permit + $85.50 . . . . . . . . . . . . $ . . . . .
ELECTRICAL PLAN-REVIEW FEE
15. See WAC 296-46B-906(9) for electrical review fees
NOTIFICATION TO LOCAL ENFORCEMENT AGENCY (NLEA)
16. Notification to local enforcement agency fee: $ 37.00
INSIGNIA FEES
17. FIRST SECTION $ 273.40
18. EACH ADDITIONAL SECTION $ 24.60
TOTAL FEES
19. Total plan review fees: Add lines 8 or 9 and 10 through 15 . . . . . . . . . . . . $ . . . . .
20. Total fees due: Includes plan fees, insignia fees, and NLEA fees . . . . . . . . . . . . $ . . . . .
21. Total amount paid . . . . . . . . . . . . $ . . . . .


Square Foot Construction Costs (BVD Table)a, b, c, and d


Group (2009 International Building Code) IA IB IIA IIB IIIA IIIB IV VA VB
A-1 Assembly, theaters, with stage 211.15 203.98 198.73 190.05 178.25 173.30 183.31 162.97 156.05
A-1 Assembly, theaters, without stage 193.16 185.99 180.74 172.06 160.31 155.36 165.32 145.04 138.12
A-2 Assembly, nightclubs 163.22 158.56 154.17 148.00 138.96 135.24 142.52 126.06 121.36
A-2 Assembly, restaurants, bars, banquet halls 162.22 157.56 152.17 147.00 136.96 134.24 141.52 124.06 120.36
A-3 Assembly, churches 195.10 187.93 182.68 174.00 162.21 157.26 167.26 146.94 140.02
A-3 Assembly, general, community halls, libraries, museums 163.81 156.64 150.39 142.71 129.91 125.96 135.97 114.63 108.71
A-4 Assembly, arenas 192.16 184.99 178.74 171.06 158.31 154.36 164.32 143.04 137.12
B Business 164.76 158.78 153.49 145.97 132.45 127.63 139.92 116.43 110.93
E Educational 176.97 170.85 165.64 158.05 146.37 138.98 152.61 127.91 123.09
F-1 Factory and industrial, moderate hazard 97.87 93.28 87.66 84.46 75.44 72.26 80.79 62.17 58.48
F-2 Factory and industrial, low hazard 96.87 92.28 87.66 83.46 75.44 71.26 79.79 62.17 57.48
H-1 High hazard, explosives 91.74 87.15 82.53 78.33 70.49 66.31 74.66 57.22 N.P.
H-2, 3, 4 High hazard 91.74 87.15 82.53 78.33 70.49 66.31 74.66 57.22 52.53
H-5 HPM 164.76 158.78 153.49 145.97 132.45 127.63 139.92 116.43 110.93
I-1 Institutional, supervised environment 164.82 159.04 154.60 147.90 135.84 132.25 144.15 121.88 117.55
I-2 Institutional, hospitals 277.07 271.09 265.80 258.28 243.90 N.P. 252.23 227.88 N.P.
I-2 Institutional, nursing homes 193.00 187.02 181.74 174.22 160.98 N.P. 168.16 144.96 N.P.
I-3 Institutional, restrained 187.72 181.73 176.45 168.93 156.64 150.82 162.87 140.63 133.13
I-4 Institutional, day care facilities 164.82 159.04 154.60 147.90 135.84 132.25 144.15 121.88 117.55
M Mercantile 121.57 116.92 111.53 106.36 96.96 94.25 100.88 84.07 80.36
R-1 Residential, hotels 166.21 160.43 155.99 149.29 137.39 133.80 145.70 123.43 119.10
R-2 Residential, multiple family 139.39 133.61 129.17 122.47 111.23 107.64 119.54 97.27 92.94
R-3 Residential, one and two family 131.18 127.60 124.36 121.27 116.43 113.53 117.42 108.79 101.90
R-4 Residential, care/assisted living facilities 164.82 159.04 154.60 147.90 135.84 132.25 144.15 121.88 117.55
S-1 Storage, moderate hazard 90.74 86.15 80.53 77.33 68.49 65.31 73.66 55.22 51.53
S-2 Storage, low hazard 89.74 85.15 80.53 76.33 68.49 64.31 72.66 55.22 50.53
U Utility, miscellaneous 71.03 67.02 62.71 59.30 52.86 49.43 56.33 41.00 39.06

a Private garages use utility, miscellaneous
b Unfinished basements (all use group) = $15.00 per sq. ft.
c For shell only buildings deduct 20 percent
d N.P. = not permitted


Table 1-A - Building Permit Fees


Total Valuation Fee
$1.00 to $500.00 $23.50
$501.00 to $2,000.00 $23.50 for the first $500.00 plus $3.05 for each additional $100.00, or fraction thereof, to and including $2,000.00
$2,001.00 to $25,000.00 $69.25 for the first $2,000.00 plus $14.00 for each additional $1,000.00, or fraction thereof, to and including $25,000.00
$25,001.00 to $50,000.00 $391.25 for the first $25,000.00 plus $10.10 for each additional $1,000.00, or fraction thereof, to and including $50,000.00
$50,001.00 to $100,000.00 $643.75 for the first $50,000.00 plus $7.00 for each additional $1,000.00, or fraction thereof, to and including $100,000.00
$100,001.00 to $500,000.00 $993.75 for the first $100,000.00 plus $5.60 for each additional $1,000.00, or fraction thereof, to and including $500,000.00
$500,001.00 to $1,000,000.00 $3,233.75 for the first $500,000.00 plus $4.75 for each additional $1,000.00, or fraction thereof, to and including $1,000,000.00
$1,000,001.00 and up $5,608.75 for the first $1,000,000.00 plus $3.65 for each additional $1,000.00, or fraction thereof




INITIAL FILING FEE (first time applicants) $66.80
   
DESIGN PLAN FEES:  
INITIAL FEE - MASTER DESIGN (code cycle), 50% of permit fee*  
INITIAL FEE - ONE YEAR DESIGN, 35% of permit fee*  
RENEWAL FEE - 10% of permit fee + $85.50
RESUBMIT FEE - 10% of permit fee + $85.50
ADDENDUM (approval expires on same date as original plan) - 10% of permit fee + $85.50
ELECTRONIC PLAN SUBMITTAL FEE $5.40 per page for the first set of plans and $1.00 per page for each additional set of plans. These fees are in addition to any applicable design plan fees required under this section.  
PLUMBING PLAN FEE, $18.00 + PER FIXTURE FEE of $6.00
MEDICAL GAS PLAN FEE, $18.00 + PER OUTLET FEE of $6.00
Note: Mechanical systems are included in the primary plan fee  
   
FIRE SAFETY PLAN REVIEW AS REQUIRED (Required for all structures that are more than 4,000 square feet and for all A, I, and H occupancy)  
MASTER DESIGN - 25% of permit fee  
One year design - 15% of the permit fee  
   
ELECTRICAL PLAN REVIEW - Find fees @ http://apps.leg.wa.gov/WAC/default.aspx?cite=296-46B-906  
   
RECIPROCAL PLAN REVIEW:  
INITIAL FEE-MASTER DESIGN (minimum 3 hours) $85.50 per hour
INITIAL FEE-ONE YEAR DESIGN (minimum 2 hours) $85.50 per hour
RENEWAL FEE (minimum 1 hour) $85.50
ADDENDUM (minimum 1 hour) $85.50 per hour
   
PLANS APPROVED BY DESIGN PROFESSIONALS - 10% of permit fee + $85.50
   
APPROVAL OF EACH SET OF DESIGN PLANS BEYOND FIRST THREE SETS - 5% of permit fee + $85.50
   
DEPARTMENT INSPECTION FEES  
INSPECTION/REINSPECTION (Per hour** plus travel time** and mileage***) $85.50
TRAVEL (Per hour**) $85.50
PER DIEM***  
HOTEL****  
MILEAGE***  
RENTAL CAR****  
PARKING****  
AIRFARE****  
   
DEPARTMENT AUDIT FEES:  
AUDIT (Per hour**) $85.50
TRAVEL (Per hour**) $85.50
PER DIEM***  
HOTEL****  
MILEAGE***  
RENTAL CAR****  
PARKING****  
AIRFARE****  
   
INSIGNIA FEES:  
FIRST SECTION $273.40
EACH ADDITIONAL SECTION $24.60
REISSUED-LOST/DAMAGED $66.80
   
OTHER FEES:  
FIELD TECHNICAL SERVICE (Per hour** plus travel time** and mileage***) $85.50
NOTIFICATION TO LOCAL ENFORCEMENT AGENCY (NLEA) $37.00
PUBLICATION PRINTING AND DISTRIBUTION OF RCWs AND WACs (One free copy per year upon request) $13.70
   
REFUND FEE $25.00
   
* Minimum plan review fee is 2 1/2 hours at the field technical service rate.  
** Minimum charge of 1 hour; time spent greater than 1 hour is charged in 1/2 hour increments.  
*** Per state guidelines.  
**** Actual charges incurred.  




[Statutory Authority: Chapter 43.22 RCW and 2011 1st sp.s. c 50. 12-06-069, § 296-150F-3000, filed 3/6/12, effective 4/30/12. Statutory Authority: Chapters 18.106, 43.22 RCW, 2008 c 285 and c 329. 08-12-042, § 296-150F-3000, filed 5/30/08, effective 6/30/08. Statutory Authority: Chapters 18.27, 18.106, 43.22, and 70.87 RCW. 07-11-128, § 296-150F-3000, filed 5/22/07, effective 6/30/07. Statutory Authority: Chapter 43.22 RCW. 07-05-063, § 296-150F-3000, filed 2/20/07, effective 4/1/07. Statutory Authority: Chapters 18.106, 43.22, and 70.87 RCW. 06-10-066, § 296-150F-3000, filed 5/2/06, effective 6/30/06. Statutory Authority: Chapter 43.22 RCW. 05-23-002, § 296-150F-3000, filed 11/3/05, effective 12/4/05. Statutory Authority: Chapters 18.27, 43.22, and 70.87 RCW. 05-12-032, § 296-150F-3000, filed 5/24/05, effective 6/30/05. Statutory Authority: Chapter 43.22 RCW and 2003 c 291. 05-01-102, § 296-150F-3000, filed 12/14/04, effective 2/1/05. Statutory Authority: Chapters 18.27 and 43.22 RCW. 04-12-048, § 296-150F-3000, filed 5/28/04, effective 6/30/04. Statutory Authority: RCW 43.22.340, 43.22.400, 43.22.432, 43.22.433, 43.22.434, 43.22.480, and 43.22.485, 2002 c 268, and chapter 43.22 RCW. 03-12-044, § 296-150F-3000, filed 5/30/03, effective 5/30/03. Statutory Authority: RCW 43.22.350, 43.22.434, 43.22.480, 43.22.500, 18.27.070, 18.27.075, 70.87.030, 19.28.041, 19.28.051, 19.28.101, 19.28.121, 19.28.161, 19.28.201, 19.28.211, 19.28.341, 2001 c 159, and chapters 43.22, 19.28, 18.27, and 70.87 RCW. 01-12-035, § 296-150F-3000, filed 5/29/01, effective 6/29/01. Statutory Authority: Chapters 43.22, 18.27, 70.87 and 19.28 RCW. 99-12-080, § 296-150F-3000, filed 5/28/99, effective 6/28/99. Statutory Authority: Chapters 18.106, 18.27 and 43.22 RCW. 98-12-041, § 296-150F-3000, filed 5/29/98, effective 6/30/98. Statutory Authority: RCW 70.87.030, 18.27.070, [18.27.]075,43.22.350 , [43.22.]355, [43.22.]434 and [43.22.]480(2). 97-11-053, § 296-150F-3000, filed 5/20/97, effective 6/30/97. Statutory Authority: RCW 43.22.340, [43.22.]355, [43.22.]360,[43.22.]432 , [43.22.]440 and [43.22.]480. 96-21-146, § 296-150F-3000, filed 10/23/96, effective 11/25/96.]