Search
480-108-110  <<  480-108-120 >>   480-108-999

WAC 480-108-120

Agency filings affecting this section

Cumulative effects of interconnections with a nameplate capacity rating greater than 300 kW but no more than 20 MW.

  Electrical companies will evaluate on an ongoing basis, but not less than once every five years, the cumulative effect, including benefits to its other customers, of interconnections made under Part 2 of this chapter on its electric system and will retain appropriate records of its evaluations.



[Statutory Authority: RCW 80.01.040 and 80.04.160. 07-20-059 (Docket UE-060649, General Order 545), ยง 480-108-120, filed 9/27/07, effective 10/28/07.]