173-186-320  <<  173-186-330 >>   173-186-340

Planning standards for crude oils.

(1) Rail plan holders carrying, handling, storing, or transporting crude oils shall have a letter of intent with a primary response contractor that maintains the resources and/or capabilities necessary to respond to a spill of oil that may weather, and sink or submerge. Such equipment shall include, but is not limited to, the following:
(a) Sonar, sampling equipment or other methods to locate the oil on the bottom or suspended in the water column;
(b) Containment boom, sorbent boom, silt curtains, or other methods for containing the oil that may remain floating on the surface or to reduce spreading on the bottom;
(c) Dredges, pumps, or other equipment necessary to recover oil from the bottom and shoreline;
(d) Equipment necessary to assess the impact of such discharges; and
(e) Other appropriate equipment necessary to respond to a discharge involving the type of oil handled, stored, or transported.
(2) The equipment shall be capable of being on scene within twelve hours of spill notification.